We have reviewed our homes at Berkeley Close to assess whether they meet the needs of our customers, now and in the future.

The houses, flats, and bungalows at Berkeley Close were built using a concrete non-traditional construction style called Reema, which means that they are not made with a conventional brick or timber frame structure. After considering the future maintenance requirements for these homes and we concluded that investing in new energy-efficient homes is the best long-term option for both us and our customers.

With this in mind, we propose to redevelop the homes that we own in Berkeley Close so that we can build new modern, energy-efficient homes in place of the existing. 

Berkeley Close 3

Updates

August 2024 - Cotswold District Council's planning committee granted us permission to redevelop our properties at Berkeley Close

Summer 2023 - we submitted our planning application to Cotswold District Council

April 2023 - we held a public consultation event where we showed our plans for the site to existing customers and the wider community

Autumn 2021 - surveys carried out in and around the proposed development site

May 2021 - we started individual consultation with customers about our plans for Berkeley Close

View our proposed plans for Berkeley Close